洁净室验收确认的方法
来源: http://bairbrepaws.com 浏览: 发布日期: 2020-12-23
洁净室洁净度的确认,有三种方式,分别为空态验收、静态验收和动态验收。空态验收指洁净室设施已经建成,但尚未安装生产设备,无材料及人员流动。静态验收设施已经建成,生产设备已经安装,并开始运行,但无生产人员。设施已按规定的状态运行,有规定的人员子在场。
There are three ways to confirm the cleanliness of clean room, which are empty acceptance, static acceptance and dynamic acceptance. Empty acceptance refers to that the clean room facilities have been completed, but the production equipment has not been installed, and there is no flow of materials and personnel. The static acceptance facilities have been built, and the production equipment has been installed and put into operation, but there are no production personnel. The facility has been operated in accordance with the specified conditions and there are specified personnel present.
三种验收方式是层层递进的,只有上一层验收通过之后,才能进行下一层的测试。然而,仅仅做基础的验收是不规范也不准确的。
After that, there is only a three-level acceptance test. However, it is not standard and accurate to only do the acceptance of the foundation.
洁净室竣工验收应在对各分部工程做外观检查、单机试运转、系统联合实运转,空态或静态条件下的洁净室性能检测和调整以及对有关的施工检车记录审核合格后进行。
The completion acceptance of clean room shall be carried out after the appearance inspection, single machine test run, system joint actual operation, clean room performance test and adjustment under empty or static conditions, and relevant construction vehicle inspection records.
各种管道、自动灭火装置及净化空调设备,空调器、风机、净化空调机组、空气过滤器和空气吹淋室等的安装应正确、牢固、严密。高中效过滤器与风管连接及风管与设备的连接处应有可靠密封。各类调节装置应严密、调节灵活、操作方便。净化空调器、静压箱、风管系统及送、回风口无灰尘。洁净室的内墙面、吊顶表面和地面,应光滑、平整、色泽均匀,不起灰尘,地板无静电现象。
All kinds of pipes, automatic fire extinguishing devices and purification air conditioning equipment, air conditioners, fans, purification air conditioning units, high efficiency air filters and air shower rooms shall be installed correctly, firmly and tightly. The connection between high and medium efficiency filter and air duct and between air duct and equipment shall be reliably sealed. All kinds of regulating devices should be tight, flexible and easy to operate. Clean air conditioner, static pressure box, air duct system and air supply and return outlets without dust. The interior wall, ceiling surface and floor of the clean room should be smooth, flat, uniform in color, free from dust, and the floor should be free of static electricity.
无菌室装修
洁净室内各类配电盘、柜和进入洁净室的电气管线管口应可靠密封。单机运转合格后,必须进行带冷(热)源的系统正常联合试运转,并不少于8h。系统中各项设备部件联动运转必须协调,动作正确,无异常现象。
All kinds of distribution boards and cabinets in the clean room and the electrical pipeline orifices entering the clean room shall be reliably sealed. After the single machine operation is qualified, the normal combined test run of the system with cold (heat) source must be carried out, which shall not be less than 8h. The linkage operation of various equipment components in the system must be coordinated, the action must be correct, and there is no abnormal phenomenon.
洁净室使用验收后,应编写使用验收报告,其主要内容有:
After the use acceptance of clean room, the use acceptance report should be prepared, which mainly includes:
1、洁净室中各种设施(包括生产工艺设备)等的开启状态描述;
1. description of opening status of various facilities (including production process equipment) in clean room;
2、测试的洁净室(区)人员及其活动情况的描述;
2. description of the clean room (area) personnel tested and their activities;
3、分项测试记录及分析意见(包括测试点位置、座标等);
3. Itemized test records and analysis opinions (including test point location, coordinates, etc.);
4、测试仪器的有效校验证书;
4. Valid calibration certificate of test instrument;
5、洁净室的验收出具相关结论。
5. Relevant conclusions should be issued for the acceptance of clean room.